Bruce Street in Inverloch get $160,000 kerb renewal over March 2023 from Bass Coast Shire Council
Kerb renewal on Bruce St. Inverloch, costing $160k, by Super Paving Vic Pty Ltd. Driveway access restricted, updates on council's website, completion expected Apr. 2023.
Bass Coast Shire is set to commence kerb renewal and associated works on Bruce Street Inverloch in mid-March 2023. The project is expected to cost approximately $160,000 and will be funded through the council's adopted Capital Works Kerb Renewal Program 2022/23. Super Paving Vic Pty Ltd has been appointed as the contractor through the annual supply contract process.
Road pavement will be reconstructed with asphalt surfacing, driveway access restricted for four days during concrete pouring
Road reconstruction project
The works will involve the removal and installation of about 300 metres of barrier kerb and drainage lines on the south and northeast side of the road, including some laybacks into driveways.
The reconstruction of road pavement one metre in front of the new sections of kerb and channel will also be carried out, including asphalt surfacing. As part of these works, new concrete may be placed through landowner's driveways.
Access to properties will be restricted for a four-day period following the pouring of the concrete kerb to allow it to be set properly before any vehicles can use their driveway. Appropriate traffic and pedestrian control measures will be implemented onsite during these works.
Project communication updates
The community, residents, businesses, and other stakeholders will be kept up to date with the project via council's website. The use of heavy plant and machinery, including noisy and vibration works for construction, will be in operation during the project. The project is expected to be completed in late April 2023, subject to favourable weather, contractor availability and material supply.
Council advises nearby residents who may be impacted by these works to be mindful of the construction zone and appreciate that access will be restricted for safety reasons. Our contractor will notify those who may be affected by these works in advance.
The renewal of this section of Bruce Street Kerb and Channel ensures that council's road network is sustainable and will continue to provide appropriate levels of service for road users well into the future.
Pictures from Bass Coast Shire website.
Source: www.gippsland.com
Published by: news@gippsland.com
Community feedback wanted on Wellington Shire Council draft 2024/25 budget by 6 May 2024
East Gippsland Shire Council starts remediation of Bastion Point groyne rock wall to address its deterioration
Photo contest winners from West Gippsland Catchment Management Authority showcase regional waterway beauty
Wellington Renewable Energy Impact Study prioritises community input in renewable energy decisions and transition
East Gippsland Shire Council makes the expanded mobile library service permanent following successful trial
Search for new East Gippsland Water Managing Director as as Steve McKenzie East not to do another term after navigating bushfires and pandemic
Community feedback wanted on Latrobe City Council draft 2024/2025 Budget by 6 May 2024
Latrobe City kindergarten enrolments for 2025 will open on 1 May 2024 with open day on 7 May 2024
Tim Bull urges increased roads and health funding from horror Budget from wasteful Allen Labor government