Feasibility study for irrigated agriculture east of Avon River progressing well says Southern Rural Water

Southern Rural Water and DELWP are conducting a feasibility study for irrigated agriculture east of Avon River, led by SMEC, with a focus on supply, environment, cost and customer impacts. A review is expected by mid-2023.

By news@gippsland - 3rd April 2023 - Back to News

Work is progressing well on the feasibility study we're leading that will inform discussions around the potential to develop irrigated agriculture in the area east of the Avon River. This initiative is supported by Action 7-2 within the Central and Gippsland Sustainable Water Strategy page. Since starting this project in September 2022, we've held four well-attended meetings with our customer and stakeholder reference group to ensure diverse voices and local knowledge is considered as part of this study.

Feasibility study for irrigated agriculture east of Avon River progressing well, storage options being explored

Feasibility study for irrigated agriculture east of Avon River progressing well, storage options being explored

Water delivery and storage

We now understand how much water can be potentially delivered to an expanded area, and the storage requirements to ensure reliability can be maintained. Studies show that to deliver 6 gigalitres (GL) of water to the area east of the Avon River, almost 2GL of storage is required. The project is now exploring the functional design options, including the size of a publicly funded balancing storage.

At this stage, we're assessing three different design options, all based on a balancing storage capacity of 125 megalitres (ML). This means that to ensure 6GL can be delivered reliably, irrigators would need to make sure they have suitable on-farm storage to make up the storage shortfall.

Avon flow potential

We are currently completing work to understand the potential for flow recovery in the Avon River either by irrigation water source substitution (i.e. irrigators only use their Avon River entitlement as back up because they have access to a higher reliability supply), or direct benefit (additional water released into the river). So far, investigations suggest there is scope to improve flows in the Avon with the proposed scheme.

We have completed a desktop assessment around the potential to use the Avon River as a conduit to supply additional water to boost irrigation in the shorter term while we continue to assess the potential for a pipeline delivery network. We found this wasn't feasible for several reasons, the main one being that it's not supported by current government policy.

Once the preferred design option is identified, we will work through the environmental planning, cultural heritage, and economic assessments and hope to complete this by the middle of the year. For further information about this project visit Macalister/Avon Irrigation Development Project page.

Pictures from National Water Grid website.


Source: http://gippsland.com/

Published by: news@gippsland.com



Edit this news article




Baw Baw Bass Coast Cardinia East Gippsland Latrobe City South Gippsland Wellington
© 2001-2024 gippsland.com Print this page | Subscribe to Newsletter | Feedback / Inquiries | Login
Care has been taken in compiling the component parts of this website. However, Gippsland.com does not warrant or represent that the website is free from errors or omissions, that the qualifications claimed by an advertiser are valid or that the published details of any advertiser are as stated on the website. Please review the full statement of our Terms and Conditions of Service and disclaimer.