Gippsland Water marked a major milestone recently as the Gippsland Water Factory anaerobic covers were replaced

Gippsland Water has safely replaced ageing covers on its complex industrial wastewater lagoons at Gippsland Water Factory near Morwell, marking an Australian first for pulp mill waste treatment lagoon upgrades.

By news@gippsland - 4th July 2025 - Back to News

Gippsland Water has completed critical upgrade works on one of its most complex industrial assets, at the Gippsland Water Factory. The ageing covers on the two industrial wastewater lagoons were replaced at the large-scale wastewater treatment facility near Morwell, which treats waste from Opal's Maryvale Mill.

Gippsland Water marked a major milestone recently as the Gippsland Water Factory anaerobic covers were replaced

Gippsland Water marked a major milestone recently as the Gippsland Water Factory anaerobic covers were replaced

Wastewater safety milestone

Industrial waste at the Gippsland Water Factory is treated in the lagoons, by creating an anaerobic environment (no oxygen), which allows microorganisms to break down waste and capture odours and gases before it progresses for further treatment. Due to the potential risks associated with the concentrations of these gases, thorough planning and stringent safety measures were required.

Acting managing director Nic Moss said the cover replacements were a first for the organisation and potentially for the wider water sector with no examples of covers being replaced on lagoons treating pulp and paper mill waste within Australia. "The successful completion of this project is a testament to the fantastic talent and resources we have here at Gippsland Water," Mr Moss said.

"This site is one of the most critical assets we manage and replacing these covers required a lot of planning, technical analysis and safety mitigation measures. Odour modelling and monitoring were also undertaken to ensure it was safe and there were no impacts on the wider community," Mr Moss said.

Safety collaboration success

Mr Moss said simulated shutdowns of the lagoons prior to work presented a better understanding of how the biological process would behave. "We worked closely with industry experts to ensure that the project could be completed safely, this included planning for different scenarios and undertaking simulated shutdowns. The simulation results were used to inform the actual shutdown of the lagoons to ensure the safe replacement of the covers, by slowing the biological activity and making the microorganisms dormant."

Mr Moss said the project was an example of the strong safety culture at the organisation. "We knew these covers had to be replaced to ensure safe operations and many teams throughout the organisation came together to provide advice, support and work through the complexities. This project is a testament to the safety culture at Gippsland Water, and we should be proud of the outcome."

The Gippsland Water Factory also treats domestic wastewater for numerous towns including Morwell, Traralgon, Churchill, Boolarra, Glengarry, Rosedale and Toongabbie. For more information, visit Gippsland Water website.

Pictures from Gippsland Water website.


Source: http://gippsland.com/

Published by: news@gippsland.com



Edit this news article




Baw Baw Bass Coast Cardinia East Gippsland Latrobe City South Gippsland Wellington
© 2001-2025 gippsland.com Print this page | Subscribe to Newsletter | Feedback / Inquiries | Login
Care has been taken in compiling the component parts of this website. However, Gippsland.com does not warrant or represent that the website is free from errors or omissions, that the qualifications claimed by an advertiser are valid or that the published details of any advertiser are as stated on the website. Please review the full statement of our Terms and Conditions of Service and disclaimer.