East Gippsland Water to install new water main to secure Lakes Entrance supply and support of future growth

East Gippsland Water will replace a key water main under North Arm to support Lakes Entrance growth, improve reliability, and protect the environment, with construction scheduled from October to Christmas.

By news@gippsland - 27th May 2025 - Back to News

A water main linking Kalimna and Lakes Entrance, which runs down the escarpment and under North Arm will soon be replaced and upgraded by East Gippsland Water to accommodate population growth. The water main crosses North Arm at Marine Parade, near the Princes Highway, and is one of only two water mains that provide potable water to Lakes Entrance.

East Gippsland Water will upgrade the key Kalimna - Lakes Entrance water main to ensure future reliability and meet growing community demand

East Gippsland Water will upgrade the key Kalimna - Lakes Entrance water main to ensure future reliability and meet growing community demand

Ensuring future supply

General Manager Sustainability and Infrastructure Neville Pearce said the Lakes Entrance Water Main Expansion Project is important to the overall water supply system. "The water main at North Arm helps East Gippsland Water maintain its service levels, particularly during Lakes Entrance's peak visitor periods."

"In 2019 we found and repaired a leak in the water main. At this time we identified the need to replace the section of pipe underneath the North Arm waterway, to ensure long-term reliability and also accommodate future growth in Lakes Entrance and surrounds," Mr Pearce said.

The works will be visible at Point Road, Kalimna, and the North Arm Apex Park boat ramp off Marine Parade, Lakes Entrance. "One of East Gippsland Water's key responsibilities is to look to the future needs of our communities. For this project, we are installing a larger water main than the existing pipe to service the forecast population growth in the region," Mr Pearce said.

Waterway works scheduled

The water main will be replaced using horizontal directional drilling for the 450-metre-long section underneath the waterway. An additional 170-metre-long section will be replaced using open trenching. "We are scheduling these works to avoid the peak tourism period. Lakes Entrance is a major tourist destination, so we are conscious to minimise disruption during the peak summer period."

"The project is also located within the Gippsland Lakes Ramsar site. As an organisation closely aligned with environmental sustainability, we are committed to ensuring we do not impact this highly valuable ecological area," Mr Pearce said.

The project's design is almost complete. Tendering for the work is expected to take place in July to August, with construction planned to begin in October this year and be complete before Christmas. For more information contact us on 1800 671 841.

Pictures from East Gippsland Water website.


Source: http://gippsland.com/

Published by: news@gippsland.com



Edit this news article




Baw Baw Bass Coast Cardinia East Gippsland Latrobe City South Gippsland Wellington
© 2001-2025 gippsland.com Print this page | Subscribe to Newsletter | Feedback / Inquiries | Login
Care has been taken in compiling the component parts of this website. However, Gippsland.com does not warrant or represent that the website is free from errors or omissions, that the qualifications claimed by an advertiser are valid or that the published details of any advertiser are as stated on the website. Please review the full statement of our Terms and Conditions of Service and disclaimer.