Port of Sale Moorings Project with sea wall and jetties adopted by Wellington Shire Council
The $1.7 million upgrade to the Port of Sale boat moorings has begun, including a new sea wall, 18 jetties, and improvements to waterfront access and amenity, the project will be completed by late 2023 in three stages.
Construction is now underway on the $1.7 million upgrade to the Port of Sale boat moorings, located in the heart of Sale at the popular Port of Sale cultural precinct. This is the first major investment project identified in the Port of Sale Master Plan, which will include significant upgrades to the West Bank of the Port, including better access to moored boats and improvements to the overall amenity and accessibility along the waterfront.
Moorings unavailable during stages, council worked with Boat Club to minimise disruption, while boat ramp limited to one lane
Enhanced port facilities upgrade
The Port of Sale Master Plan was first adopted by council in October 2021 following extensive engagement with the community and key stakeholders. It sets out a strategic vision for the precinct that will support the economic and sustainable growth of the Shire. Works will take place over three stages and include a new concrete sea wall with 18 double berth jetties, with new stern piles.
The upgrades will be delivered by the Carter Marine Group, who are experienced in the design, construction, and installation of jetties. Each stage will take approximately ten weeks to complete, with the project expected to be completed late 2023.
During each stage, moorings will be unavailable for use. Council has worked proactively with the Port of Sale Boat Club throughout the design process including arranging for works to be staged to minimise disruption. Recreational boating users should be aware that the Port of Sale boat ramp will be limited to one lane during the project.
Port upgrade enhances amenities
Wellington Shire Council Mayor Ian Bye said that council is really excited to see this project get underway. "This is the first significant upgrade to the Port of Sale since the redevelopment of the Wellington Centre to a state-of-the-art cultural hub in 2018. Once complete, the long advocated for improvements will better meet the needs of mooring holders, the Port of Sale Boat Club and improve the overall amenity of the precinct." Cr Bye said.
Commodore of the Port of Sale Boat Club, Bryan Cumming further commented, "The Port of Sale Boat Club would like to thank the Wellington Shire for allowing them to be part of this project. This project will benefit greatly to all those that will use this area in the future".
For more information about the Port of Sale Moorings Project, please visit Port of Sale Moorings Project page or contact council's Development team on 1300 366 244. To view the Port of Sale Master Plan, please visit Port of Sale - East Bank Redevelopment Study page.
Pictures from Port of Sale website.
Source: www.gippsland.com
Published by: news@gippsland.com

Community feedback strengthens Wellington's Road Management Plan, highlighting priorities for road upgrades

East Gippsland kids invited to join and send entries for National Water Week poster competition by 12 September 2025

Future Wellington Community feedback shapes draft plans, final input invited before 16 July 2025

Gippsland Water commits to keeping customer bills affordable despite cost of living pressures

Have your say on Latrobe's draft Domestic Animal Management Plan 2026 - 2029 until 29 July 2025

Latrobe City Council endorses new Council Plan and Community Vision 2025-2029 to guide Latrobe's future growth

Wellington Shire Councillors advocate for region's needs at National Local Government Assembly in Canberra on 24 - 27 June 2025

East Gippsland tourism and hospitality masterclass to build sustainable, resilient businesses and grow positive

Southern Rural Water celebrates 30 years of service with modernisation, partnerships and sustainable water