Gippsland › Latest news › Bass Coast Local News

Study shows erosion impacts on Kilcunda foreshore in Bass Coast Shire

The Kilcunda Foreshore Erosion Options Assessment Report has recently been released, outlining a study into the impacts of erosion on the Kilcunda foreshore.

By news@gippsland - 10th December 2021 - Back to News

Bass Coast Shire Council engaged a coastal engineer to undertake the study, to inform the longer-term response to erosion at the Kilcunda Surf Beach, near the Lionel Rose car park. The study investigated the coastal processes influencing erosion in this location and assessed the risk to built public assets. The study also reviewed the options available for the management of ongoing coastal erosion.

This area has seen rapid wave erosion in recent times, which has already impacted public assets such as beach access tracks and the Bass Coast Rail Trail

This area has seen rapid wave erosion in recent times, which has already impacted public assets such as beach access tracks and the Bass Coast Rail Trail

Re-routing a section of the pathway

Earlier this year, council moved a section of the Rail Trail three metres inland, as a short-term response to the advancing erosion. Bass Coast Shire Mayor, Cr Michael Whelan said that in order to protect vital community assets like the Rail Trail from further damage, the Report recommends the option of a 'staged retreat'.

Cr Whelan said, "This involves initially moving any other vulnerable sections of the rail trail a few metres inland, still on the dune crest. If the rate of erosion continues to a point where moving the rail trail on the dune crest is no longer possible, the report recommends re-routing a section of the pathway further inland, well behind the dune."

Re-alignment of the rail trail

Cr Whelan said that Council will continue to monitor the rate of erosion and deposition at the beach in Kilcunda. "More recently, we have seen that the beach has been building back up at the project site and grasses have started to return to the embankment, so it is possible that path realignment works might not be required in the short-term," Cr Whelan said.

Council officers continue to monitor the area closely, and are now working to deliver on the recommendations of the report. This includes design work and permits for a re-alignment of the rail trail, so that further works can proceed promptly if required.

For more information or to view the Report, visit Bass Coast erosion control.

Pictures from Bass Coast Shire website.


Source: www.gippsland.com

Published by: news@gippsland.com



Edit this news article




Baw Baw Bass Coast Cardinia East Gippsland Latrobe City South Gippsland Wellington
© 2001-2024 gippsland.com Print this page | Subscribe to Newsletter | Feedback / Inquiries | Login
Care has been taken in compiling the component parts of this website. However, Gippsland.com does not warrant or represent that the website is free from errors or omissions, that the qualifications claimed by an advertiser are valid or that the published details of any advertiser are as stated on the website. Please review the full statement of our Terms and Conditions of Service and disclaimer.