Jam Jerrup drainage upgrades along Foreshore Road
Bass Coast Shire Council will carry out drainage renewal works along Foreshore Road in Jam Jerrup in August.
Work is expected to begin in early August and take around four weeks to complete, subject to favourable weather conditions. This $70,000 project is supported by the Victorian Government through the Distinctive Areas and Landscapes Capital Funding Program 2019/2020.
The crumbling cliffs at Jam Jerrup, showing part of the rock wall
Minimising stormwater runoffs
This project is part of a partnership with the Department of Environment, Land, Water and Planning and Council. The Department has recently completed seawall protection works at Jam Jerrup.
The aim of this project is to minimise stormwater runoff flowing across the newly constructed seawall embankments and to improve the quality of road stormwater runoff and direct the stormwater flow along Foreshore Road, to discharge at the outfall.
Soakage pit installation
The project will include the installation of a new stormwater drainage pit at Bay Road intersection and the re-alignment of existing stormwater property outlets as required, as well as the installation of a soakage pit.
Soakage pits are a water sensitive urban design mechanism that rely on the stormwater principles of retention and filtration. Soakage Pits are located at the end of a stormwater drainage network, buried underground and out of sight.
The soakage pits collect the incoming storm water and store it, while the water slowly percolates into the surrounding ground through a filtration process. This means that water is directed off the surface and stored underground where it slowly seeps into the earth.
Safety measures will be in place
Traffic and pedestrian measures will be in place throughout the duration of the works. Road users may experience minor delays. Every effort will be made to minimise disruptions.
For more information on this project please visit foreshore road renewal works, or contact Council's Infrastructure Delivery Team on 1300 BCOAST (226 278) or (03) 5671 2211 or email basscoast@basscoast.vic.gov.au.
Pictures from Bass Coast Shire website.
Source: www.gippsland.com
Published by: news@gippsland.com
Community feedback wanted on Wellington Shire Council draft 2024/25 budget by 6 May 2024
East Gippsland Shire Council starts remediation of Bastion Point groyne rock wall to address its deterioration
Photo contest winners from West Gippsland Catchment Management Authority showcase regional waterway beauty
Wellington Renewable Energy Impact Study prioritises community input in renewable energy decisions and transition
East Gippsland Shire Council makes the expanded mobile library service permanent following successful trial
Search for new East Gippsland Water Managing Director as as Steve McKenzie East not to do another term after navigating bushfires and pandemic
Community feedback wanted on Latrobe City Council draft 2024/2025 Budget by 6 May 2024
Latrobe City kindergarten enrolments for 2025 will open on 1 May 2024 with open day on 7 May 2024
Tim Bull urges increased roads and health funding from horror Budget from wasteful Allen Labor government