First stage of Omeo Mountain Bike Trail that will put alpine towns on the map to be completed by December 2023
Work is set to begin on a network of trails that will turn Omeo into a mecca for mountain bikers.
The Omeo Mountain Bike Trails will put the Alpine town on the map as a year-round active tourism destination and capture nationwide demand for outdoor adventure. Mayor Cr Mark Reeves said the Omeo Mountain Bike Trails will create an eco-friendly tourism drawcard for the town. "It will see more people discover the unspoilt beauty of Omeo and the High Country and provide a boost for local businesses and jobs."
The Omeo mountain bike trails will meet Mountain Bike Australia criteria for national events with event plans underway for when Stage 1 is completed
Opportunity for cycling tourism
Cr Reeves said, "The local community has embraced the project and look forward to introducing visitors to the spectacular landscapes that surround their town. This is a major project for not only Omeo, but East Gippsland and Victoria. It puts us in the conversation of national and world-class mountain biking."
"This will create opportunities for cycling tourism, economic diversity and growth in the high country, and major events. The investment by all three tiers of government, and the push of the community will make this a success and the benefits will flow accordingly." Cr Reeves said.
Work on Stage 1 will begin late this month, with contractor Common Ground Trails, who built the Pump and Skills Track in Livingstone Park, using a workforce of current staff and locals for the build. It is expected the first trail will be available for riding by December this year, with Stage 1 completed by December 2023.
Stage one work inclusions
The first stage will include:
- 56 kilometres of cross-country and downhill gravity trails
- Switchback climbs for over 500m up nearby Mt Mesley
- An easy loop trail parallel to the Great Alpine Road that leads to the Historical Oriental Claims area
- A descending trail of over 500 vertical metres from the summit of Mt Sam linking to Mt Mesley and finishing in Livingstone Park
In April 2021, East Gippsland Shire Council resolved to award the contract for the Omeo Mountain Bike Trail Construction to Common Ground Trails Pty Ltd for Stage 1 - 56.3km of trails.
However, in the time between contract consideration by council (16 March 2021) and council's ability to finalise the contract (due to a VCAT hearing in November and determination in December 2021),the construction environment has changed considerably.
Addressing delays
The project has also incurred additional costs associated with native vegetation management and legal and associated costs relating to the VCAT hearing. Significantly, this includes mandated changes to a parcel of Crown land being used to meet native vegetation offset requirements, and a requirement to pay for these new costs upfront, rather than in annualised instalments.
At this week's council meeting (5 April 2022), council supported a budget variation to address the above. Cr Reeves said cost escalations on projects in the current environment are not lost on council. "Delays and price escalations were not of council's making. The significance and benefit of this project means we are committed to seeing it completed," Cr Reeves said.
Project made possible
This project has been funded by council, the Victorian government's Regional Tourism Infrastructure Fund, and the federal government's Building Better Regions Fund and more recently the Local Roads and Community Infrastructure Fund.
The project has been made possible through the strong collaborative efforts of the Department of Environment, Land, Water and Planning, Parks Victoria and a dedicated group of community supporters working with council.
Pictures from East Gippsland Shire Council Facebook page.
Source: http://gippsland.com/
Published by: news@gippsland.com

Community feedback strengthens Wellington's Road Management Plan, highlighting priorities for road upgrades

East Gippsland kids invited to join and send entries for National Water Week poster competition by 12 September 2025

Future Wellington Community feedback shapes draft plans, final input invited before 16 July 2025

Gippsland Water commits to keeping customer bills affordable despite cost of living pressures

Have your say on Latrobe's draft Domestic Animal Management Plan 2026 - 2029 until 29 July 2025

Latrobe City Council endorses new Council Plan and Community Vision 2025-2029 to guide Latrobe's future growth

Wellington Shire Councillors advocate for region's needs at National Local Government Assembly in Canberra on 24 - 27 June 2025

East Gippsland tourism and hospitality masterclass to build sustainable, resilient businesses and grow positive

Southern Rural Water celebrates 30 years of service with modernisation, partnerships and sustainable water