Fingerboards Mineral Sands Project Environmental Effects Statement (EES) and Inquiry and Advisory Committee (IAC) hearing cost East Gippsland Shire Council $730,688
Total external cost hearing of the fingerboards mineral sands project.
East Gippsland Shire Council has confirmed the total external cost associated with its involvement in the Fingerboards Mineral Sands Project Environmental Effects Statement (EES) and Inquiry and Advisory Committee (IAC) hearing. Total hearing costs amounted to $730,688 at the conclusion of the process in July, after 10 weeks, 36 hearing days and three directions hearings.
Pre-hearing preparation costs have been previously disclosed, with an additional for the review of the EES and preparation of the project technical review submitted by council's consultant
Cost of hearing
The cost of council's legal representation for the hearing is summarised as follows (all costs ex GST):
- IAC hearing legal representation: $585,473
- Expert witnesses: $145,215
- Total: $730,688
In February 2021, Council estimated hearing costs at $490,000 for the initial 31-day expected hearing timeline for legal representation only. Council was later briefed that the cost of legal representation for the hearing could rise to approximately $700,000, given an increase in preparation and hearing days as a result of more information being presented by other parties, the proponent introducing new material and revised expert statements and requests for adjournment.
Maintaining transparency
Representation at the hearing was a decision of council in December 2020. Chief Executive Officer Anthony Basford said participation in the hearing came at a cost, but Council's continued representation was important for the community. "It's important for the local government to be at the table to provide feedback on the issues identified through the technical review and argue for good environmental, social and economic outcomes," Mr Basford said.
Council maintained its transparency with the community throughout the process and Councillors were kept fully briefed on all costs associated with the IAC hearing throughout. Pre-hearing preparation costs have been previously disclosed, with an additional cost of $140,000 for the review of the EES and preparation of the project technical review submitted by Council's consultant SLR Consulting Pty Ltd. This brings the total cost of Council's involvement to $870,989.
Significant disadvantage
Mr Basford said participation in the IAC allowed Council to be able to highlight the deficiencies of the EES at the hearing. "We are now undertaking an advocacy process on the need for an urgent review of the EES process which, in its current form, puts local government and the communities it represents at a significant disadvantage in terms of the financial, social and human resource implications."
"We've written to several people including the Premier and the Minister for Planning and the Mayor, Cr Mendy Urie, has also taken the issue to the Local Government Mayoral Advisory Panel. A few possible solutions we're proposing to this complex issue include early planning to help reduce costs, funding to support the continuation of local government 'business as usual' functions and Technical Reference Group changes to support our ability to seek input from the community." Mr Basford said.
All details and recordings relating to the hearing can be found on the Engage Victoria website. This includes Council's full submission in the 'Tabled Documents' section of the webpage.
Pictures from Committee for Gippsland website.
Source: http://gippsland.com/
Published by: news@gippsland.com
More frontline police officers in Gippsland urgently needed to deter criminal activity
Applications for Victorian Landcare Grants for West Gippsland open until 30 April 2024
Barry Beach Marine Terminal anticipates pivotal shift in maritime operations to soon host world largest construction vessel
Corinella Boating and Angling Clubhouse needs funding gap bridged so serving multiple community groups and continue
Luke Connell appointed Director of Planning and Development for Baw Baw Shire Council
Latrobe City engages with Net Zero Authority to advocating transition plan and help secure regional prosperity
Martin Cameron presses Minister Ros Spence for clarity amid club concerns in Latrobe Valley on sport voucher program
New fresh food tax bill threatens higher living costs and will be detrimental to Gippsland families and farmers
To avoid disillusionment in Federal Labour government its housing and power promises must be fulfilled